Established 1968

Mechanical and Civil Engineering Contractors Company

Civil Construction

Mace specialises in utility infrastructure works particularly Sewerage, Storm and Potable water. We can undertake all sizes of works from water main diversions to long distance pipelines.

Civil Construction

Mechanical Works

Recently MACE have been active in projects involving the provision, operation and maintenance of a wide variety of Mechanical Process plant, in particular extensive pumping and pipework systems, both…

Mechanical Works

Pipe Rehabilitation

In the last 7 years, MACE successfully completed the rehabilitation of some 45 km of sewers irrigation lines ranging in size from 400 mm to 1600 mm diameter as well as other smaller diameter sewers…

Pipe Rehabilitation

Relining of Pipelines

Over the last decade. MACE built a highly trained team of professionals capable of providing a complete service of design, engineering and execution of the aforementioned activities.

Relining of Pipelines

MACE Responds to Emergency Call Out

MACE were recently called on by ADSSC to attend a high profile emergency sewage flooding incident.  We needed to fix a fractured sewer force main caused by a building contractor.  The problem began last Tuesday (3rd Jan) when the contractor broke through a main sewer pipe in the area of Mohammed Bin Zayed City, east of Mussafah, which was carrying pumped raw sewage from Abu Dhabi Island to the main pumping station on the mainland.

The main Abu Dhabi pumping station had to divert flows, which increased demand on the remaining network, as a result, there were times when the network could not cope. This increased the pressure on the MACE teams struggling with the spilled sewage and fractured pipe over 6 meters below the sand.

The first task was to excavate primarily by hand to expose the two pressure mains, once the pipes had been positively located a larger and deeper excavation using sheet trenching to stop the sides from collapsing could be installed. Following another day of 24 hour hand digging the broken pipe was fully exposed and a repair collar was fitted. The pumps on the island were then restarted and the main pushed up to full pressure for several hours to ensure that not even the smallest leak remained. ADSSC were then able to confidently order the excavation backfilled and our equipment removed from site.  All the works were completed in less than three days by the MACE team working 24 hours a day until the job was finished. 

More Articles